Loading questions
Loading questions
Generated Sep 18, 2026, 5:46 PM
I put the chance of YES at 45.7%. Boeing has enough calendar time, but on September 16 it had not cleared either gate it named for Rate 52: stable Rate 47 wing flow in Renton and a certified, producing Everett North Line (Boeing transcript, September 16, 2026). The cutoff sits ten days before my median transition date, so Q2 2027 is more likely than Q1.
The resolution bar is lower than producing 52 aircraft in a calendar month. Boeing only needs to begin the overall program transition by March 31, 2027. Boeing used that distinction for Rate 47: its July results said the transition began during Q2, although Ortberg later said the system was not stable at 47 (Boeing Q2 results, July 28, 2026; September transcript).
The schedule has slipped. A July Reuters report described Boeing as aiming for Rate 52 in early 2027, while the September 16 direct management statement committed only to the next rate occurring in 2027 after acknowledging slower-than-expected Rate 47 stabilization (Reuters, July 6, 2026; Boeing transcript, September 16, 2026).
The table gives the full public series of 737 program-rate checkpoints I use, from Boeing’s 2010 baseline through September 18, 2026. These are stated production rates or operating states, not deliveries. The coverage window is 2010–September 18, 2026, with 16 checkpoints; several older dates have quarter-level precision.
| Date | Disclosed 737 production state |
|---|---|
| 2010 | Baseline of 31.5 aircraft per month (Boeing, February 4, 2014) |
| October 18, 2011 | Began production at 35 per month (Boeing) |
| January 29, 2013 | Began production at 38 per month (Boeing) |
| February 4, 2014 | Began production at 42 per month (Boeing) |
| Q3 2017 | Increased to 47 per month (Boeing Q3 results, October 25, 2017) |
| Mid-2018 | Increased to 52 per month (Boeing, January 8, 2019) |
| April 15, 2019 | Reduced from 52 to 42 after the MAX grounding (Boeing Q2 2019 Form 10-Q) |
| January/May 2020 | Production suspended, then restarted at low rates (Boeing Q3 2020 Form 10-Q) |
| Q2 2021 | Producing at about 16 per month (Boeing Q2 results) |
| Q2 2022 | Increased to 31 per month (Boeing Q2 results) |
| Q2 2023 | Began transitioning to 38 per month (Boeing Q2 results) |
| Q4 2023 | Reported at 38 per month (Boeing Q4 results, January 31, 2024) |
| January 24, 2024 | FAA halted further MAX production expansion at the then-current rate (FAA) |
| Q2 2025 | Reached 38 again after the 2024 disruption (Boeing Q2 results) |
| October/Q4 2025 | FAA and Boeing agreed on Rate 42; Boeing increased to 42 during Q4 (Boeing Q3 results; 2025 annual report) |
| Q2 2026 | Began transitioning from 42 to 47 with FAA concurrence (Boeing Q2 Form 10-Q) |
The closest analogue is the only prior 47-to-52 step, so its directly comparable sample size is just N=1. Boeing went to 47 during Q3 2017 and to 52 around the middle of 2018, a roughly nine-to-twelve-month interval. The present deadline is 308 days, or 10.1 months, after the May 27, 2026 Rate 47 capstone. Historical cadence alone therefore gives about even odds.
The current step is harder. Rate 47 used the existing Renton system. Rate 52 requires Renton to stabilize and Everett to complete conformity work. In April, Boeing said the North Line would build initial aircraft to demonstrate conformity to the FAA; in September, Ortberg specified four initial aircraft and said the line must be certified and producing before Rate 52 (Boeing Q1 transcript, April 22, 2026; September transcript). Boeing’s July 10 update showed actual progress—the first fuselage was loaded in late June and a second aircraft had entered the line—but did not provide a certification date (Boeing North Line update).
The wing-shop trend is the strongest negative signal. On May 27, Ortberg expected Rate 47 stabilization within a couple of months. On July 28, he said wing-flow improvements were in place and looked good. By September 16, he said Boeing had not seen the expected flow gains on schedule and that the wing shop remained the constraint (May transcript; Q2 transcript; September transcript). That is observed slippage in a prerequisite, not generic caution.
Supplier and regulatory signals are better. Ortberg said CFM engines and the near-term external supply chain were ready for the next ramp. The FAA also restored Boeing’s authority to issue airworthiness certificates for all MAX aircraft on July 20 after eight months of comparable quality findings, while retaining inspections and production-system oversight (Boeing transcript, September 16, 2026; FAA, July 17, 2026). Neither fact constitutes Rate 52 concurrence.
Labor is a downside tail. In August, SPEEA’s professional and technical units rejected the first offers by 64.25% and 71.87%; strike authorization passed by 87.82% and 89.71%. A revised final offer was awaiting a September 24–October 1 vote at the forecast cutoff (SPEEA vote results, August 21, 2026; SPEEA final-offer schedule). I treat a production-relevant stoppage as a material risk, not the central case.
My main timing model uses 5,000,000 simulated paths over September 18, 2026–March 31, 2027. It models the transition date as , where is residual readiness and concurrence time and represents disruptions. I use a January 11 median for Rate 47 stabilization, a February 10 median for North Line certification and productive operation, 0.40 correlation between the gates, and a residual lag with a 20-day mode and 60-day maximum. I add a 13% labor-delay branch and a 10% other quality-or-supply-delay branch. These are subjective inputs anchored to the disclosed milestones, not measured frequencies.
That model returns 45.3%, with a median transition date of April 10, 2027. Moving both gate medians 15 days earlier raises the result to 54%; moving both 15 days later lowers it to 37%. A historical-cadence cross-check gives 50%, while a management-language check gives 40%. Weighting those estimates 70%, 20%, and 10% gives .
Everett is not an independent escape from the Renton bottleneck. All MAX wings are still built in Renton, including wings for Everett aircraft, so the new line adds final-assembly capacity without removing the current system-wide choke point (Boeing transcript, September 16, 2026). The North Line is the long pole in about two-thirds of my simulations.
The resolution wording cuts both ways. Boeing can resolve YES without stable output at 52 because its process pulses the factory at a higher cadence and uses blank positions before stabilization (Boeing transcript, May 27, 2026). But a 2021 FAA settlement required advance FAA access to production-readiness assessments and underlying data at least 30 days before covered rate increases, which could make a late-March transition depend on readiness work being largely complete around March 1 (FAA settlement agreement).
Hover a data point to trace its series, or click to view the forecast generated at that time.
Signed forecast receipt
Signed Sep 18, 2026, 5:46 PM with ed25519 key preseen-prod-ed25519-20260523 and externally timestamped Sep 18, 2026, 5:46 PM.
sha256:8bb09b99fe678a...42444549ae