Forecast report
When will the construction of Jeddah Tower be complete?
Forecast
Median forecast: Apr 1, 2029; 80% interval: Jul 1, 2028 to Aug 25, 2032.
Distribution
Analysis
TL;DR
My median completion-declaration date is March 27, 2029. The forecast puts 39.3% before January 1, 2029, 73% before January 1, 2030, and 4% after December 31, 2037. The August 2028 project target is physically possible, but the facade and post-topping work make 2029 the most likely year.
Context
Jeddah Tower is a live construction project again. On October 2, 2024, Jeddah Economic Company signed a SAR 7.2 billion completion agreement with Saudi Binladin Group; SAR 1.1 billion covered earlier work, the disclosed program was 42 months, and 63 of 157 floors had been completed. Concrete pouring resumed on January 20, 2025. By September 1, 2026, the contractor reported Level 113 and 454 meters.
I treat completion as the first clear declaration that the final structure and architectural envelope are finished and the tower is no longer under construction. I do not require tenant fit-out, occupancy, a public opening, or completion of Jeddah Economic City. This makes the likely resolution earlier than full commercial operation, but later than a topping-out ceremony.
Evidence
The closest precedent is Burj Khalifa. It reached Level 100 in January 2007, topped out in January 2009, and finished cladding in September 2009. Jeddah Tower reached Level 100 on April 20, 2026. A mechanical copy of Burj Khalifa's 32-month Level-100-to-cladding interval points to December 2028 for Jeddah Tower. That is close to the official target, but already leaves no allowance for Jeddah's greater height or its old stoppage.
The cleanest 550-meter-plus comparisons show that much remains after the headline structure reaches its top. The sample is small and survivorship-biased, but it is the right order of magnitude.
| Building | Late structural milestone | Shell or recognized completion | Lag |
|---|---|---|---|
| Burj Khalifa | Spire topped out, January 2009 | Cladding complete, September 2009 | 8 months |
| Shanghai Tower | Main building capped, August 2013 | Civil works complete, end-2014 | about 17 months |
| Lotte World Tower | Ridgepole raised, December 22, 2015 | Completed, February 9, 2017 | about 14 months |
| Merdeka 118 | Final roof slab, June 2021 | CTBUH completion year, 2023 | about 2.5 years |
The midpoint of those lags is roughly 15–17 months. Jeddah can beat a simple sequential model because facade, MEP, podium, and elevator work run in parallel. It can also underperform the sample because no completed building has crossed one kilometer. Broader megaproject research finds persistent schedule optimism, though those databases usually measure from the decision to build and are too pessimistic for a tower already at Level 113 (Flyvbjerg, 2014).
The restart-era milestone history shows real acceleration, but not the uninterrupted five-day cycle used in promotional summaries.
| Report date | Reported state |
|---|---|
| October 2, 2024 | Level 63; completion contract signed |
| January 23, 2025 | Concrete poured for Level 64 |
| August 14, 2025 | Core near Level 69 |
| January 6, 2026 | Near Level 80 |
| January 22, 2026 | Level 85 |
| March 25, 2026 | Level 91; about 370 meters; roughly 5,200 workers |
| April 20, 2026 | Level 100 |
| June 22, 2026 | Near Level 104; just over 400 meters |
| August 6, 2026 | Level 106; 430 meters |
| September 1, 2026 | Level 113; 454 meters |
From March 25, 2026 to September 1, 2026, the reported core advanced 22 levels in 160 calendar days, or 7.3 days per level. The contractor's five-day figure describes the active core cycle, not completion of slabs, wings, facade, and services at the same height. I use the measured 7–8 day pace for the main occupied structure, then add separate time for the upper transition, pinnacle, envelope, and closeout.
The facade is the main schedule test. Kingdom Holding reported on August 6, 2026 that more than 3,000 panels equaled about 11% of the facade. That implies roughly 27,000 panels in total and about 24,000 still to install. Finishing by August 2028 requires roughly 930–980 panels per month, depending on the unreported measurement date of the 3,000-panel figure. Burj Khalifa used close to 26,000 panels and installed its cladding from May 2007 to September 2009, also about 930 panels per month on average. The target therefore demands mature Burj-Khalifa-level facade output almost immediately. It is hard, not impossible.
Procurement is stronger than the tower's old history suggests. Jangho won a SAR 1.052 billion curtain-wall subcontract and installed the first new unit on November 30, 2025. KONE booked an order for 67 elevators and escalators on October 8, 2025. Jinggong won the main steel package above Level 120 in May 2026. These awards cut abandonment risk. They do not remove installation and commissioning risk, and the upper-steel award came only months before the core approached that zone. Mobilization also rose from roughly 5,200 workers in March 2026 to about 6,400 in the August release, which argues against an imminent stop.
Financing is active but not fully de-risked. The 2024 contract disclosure names internal funds and banking facilities, but gives no committed facility amount. Kingdom Holding's August 2026 release kept Jeddah Economic City at its year-end 2025 valuation because of real-estate-sector challenges. I treat that as a mild right-tail signal, not evidence of a near-term suspension.
The bottom-up schedule lands near the reference class. In June 2026, structural engineer John Peronto put the sky-terrace region around Level 160 roughly 60 weeks away, implying August 2027, while maintaining the August 2028 completion target. Adding about a year for the upper structure, facade catch-up, and architectural closeout produces late 2028 in the clean case and 2029 after ordinary slippage. The independent Skyscraper Center lists 2030, but it does not publish enough schedule methodology for me to treat that year as more than a cautionary outside view.
I encoded the forecast as a right-skewed mixture over elapsed time from September 4, 2026: 34.0% near the public target, centered on August 25, 2028; 39.3% routine slippage, centered on May 1, 2029; 14% larger technical or commercial delay, centered on July 1, 2030; 8% a renewed multi-year stall, centered on March 1, 2033; 1% a more severe but recoverable delay, centered on June 1, 2035; and 4% explicit cancellation, indefinite suspension, or completion beyond the upper bound. Continuous scenario tails lift the final post-2037 probability to 4.4%. The resulting 10th, 50th, and 90th percentiles are June 17, 2028, March 27, 2029, and August 24, 2032.
What's non-obvious
Most quick readings make one of two errors. The optimistic error treats Level 113 out of 157 or 167 as near completion, even though the tower was only 454 meters high on September 1, 2026, versus a planned height above 1,000 meters, and the facade was only 11% installed in the August report. The pessimistic error extrapolates 11% linearly. Curtain-wall work ramps across multiple elevations, and the tapered upper tower needs fewer panels per vertical meter.
The best single comparison is not the full construction duration of Burj Khalifa. It is the time from Level 100 to exterior completion. That benchmark points to December 2028, just four months after Jeddah's target. This is why I give August 2028 meaningful probability while keeping the median in spring 2029.
Uncertainties
- The final floor count is inconsistent. The 2024 Saudi Exchange disclosure says 157, while the Skyscraper Center says 167. Different treatment of technical levels may explain the gap, but the public record does not settle it.
- The August earnings release gives concrete, facade, and workforce figures, but not the exact observation date for each measure. I also lack authenticated public data for wing slabs, podium completion, permanent elevator installation, MEP second-fix, and commissioning. Those workstreams can move the finish date even if the core stays on pace.
- I could not authenticate an exact contractual date of August 17, 2028. The primary Saudi Exchange disclosure says 42 months, while current project reporting supports August 2028, not a specific day.
- A developer can declare construction complete before a stricter database or operator does. The resolution rule favors the earliest clear, widely accepted declaration, so wording in future announcements creates several weeks or months of irreducible date uncertainty.
Sources
- Domain Expert Search · mcp
Found 14 domain experts for 'supertall and megatall skyscraper construction schedules, facade engineering, project delays, Jeddah Tower Saudi Arabia':
- Domain Expert Research Task · mcp
Job domain_expert_research_task_e13d3f664b done after 305850ms.
- enr.com · tool
- theurbandeveloper.com · tool
- leaders-mena.com · tool
- constructionweekonline.com · tool
- en.wikipedia.org · tool
- archup.net · tool
- linkedin.com · tool
- dezeen.com · tool
- zawya.com · tool
- kone.com · tool
- origin-www.kone.com · tool
- archup.net · tool
- zawya.com · tool
- saudiweek.com · tool
- argaam.com · tool
- gulfnews.com · tool
- newsweek.com · tool
- scenenow.com · tool
- newsweek.com · tool
- newsweek.com · tool
- skyscrapercenter.com · tool
- arabianbusiness.com · tool
- leaders-mena.com · tool
- agbi.com · tool
- enr.com · tool
- newatlas.com · tool
- build-construct.com · tool
- architecturelab.net · tool
- arabianbusiness.com · tool
- saudimoments.com · tool
- bloompakistan.com · tool
- newsweek.com · tool
- masralyoum.news · tool
- newsweek.com · tool
- eyeofriyadh.com · tool
- argaam.com · tool
- archup.net · tool
- dezeen.com · tool
- concreteconnect.co.uk · tool
- kingdom.com.sa · tool
- zawya.com · tool
- thenationalnews.com · tool
- mjengohub.co.ke · tool
- architecturaldigest.com · tool
- skyscrapercenter.com · tool
- skyscraperpage.com · tool
- guest.meed.com · tool
- zawya.com · tool
Question Details
Description
This question asks for the calendar date on which construction of the Jeddah Tower (also known as Kingdom Tower) in Jeddah, Saudi Arabia is completed. Jeddah Tower is planned to exceed 1,000 meters in height and become the tallest building in the world. Construction began in 2013 but experienced long delays and a multi-year pause before resuming around 2024–2025. As of early 2026, construction has progressed past roughly 80–100 floors, with work advancing steadily again. ([jeddahconstruct.com](https://www.jeddahconstruct.com/)) Current public estimates from developers and reporting suggest a target completion around 2028, though timelines have historically shifted. ([agbi.com](https://www.agbi.com/real-estate/2025/11/jeddah-tower-world-tallest-building-homes-to-go-on-sale-in-2026/)) The question resolves to the date when the tower is officially considered complete (see criteria below).
Resolution Criteria
The question resolves to the first calendar date on which Jeddah Tower is officially declared complete by its developer (Jeddah Economic Company), the Saudi government, or widely accepted international business or construction media (e.g., Reuters, Bloomberg, Financial Times), indicating that construction has been finished. "Complete" is defined as structural and architectural construction being finished to the point that the building is no longer under construction, even if interior fit-out, tenant occupancy, or surrounding infrastructure continues afterward. If multiple dates are reported, the earliest date of a clear and widely reported declaration of completion will be used.
Fine Print
- “Completion” refers to completion of construction of the tower itself, not the broader Jeddah Economic City development. - Temporary pauses or resumptions do not affect resolution unless they change the final completion date. - Minor discrepancies between sources (e.g., ceremonial opening vs. construction completion) will be resolved in favor of the earliest clear statement that construction is finished. - If the tower is cancelled or never completed this question will resolve above the upper bound date.