Back to question

Forecast report

When will the construction of Jeddah Tower be complete?

GeneratedJuly 4, 2026 at 5:52 PM UTC
ResolutionNot specified
Question typeDate
Sources50

Forecast

Median forecast: May 8, 2029; 80% interval: Jul 1, 2028 to Apr 19, 2032.

Distribution

P10 Jul 1, 2028
Median May 8, 2029
P90 Apr 19, 2032
0.0%0.9%1.7%2.6%3.5%Jan 1, 2028Jul 2, 2030Dec 31, 2032Jul 2, 2035Dec 31, 203780% intervalMedian

Analysis

TL;DR

My median date for a construction-complete declaration is April 2029. I assign 38% probability to completion by December 31, 2028, 67% by December 31, 2029, 81% by December 31, 2030, and 4.2% after December 31, 2037. The August 2028 target is credible because the restart is real, but a one-year slip is the central case because the tower was still just over 400 meters and near the 104th floor in June 2026 (Zawya/Refinitiv, Jun. 22 2026).

Context

Jeddah Tower is active again after a long pause. On October 2, 2024, Kingdom Holding said Jeddah Economic Company had signed a SAR 7.2 billion agreement with Saudi Binladin Group to resume the tower, with about SAR 1.1 billion already paid for earlier work, 63 of 157 floors complete, and an anticipated 42-month construction period funded through internal resources and bank facilities (Kingdom Holding, Oct. 2 2024). MEED then reported that concrete pouring was set to resume on January 20, 2025, with Saudi Binladin Group carrying out the works and the superstructure about one-third complete at 63 of 157 floors (MEED, Jan. 20 2025).

The latest high-quality progress data still points to a 2028 target, but not to an easy finish. Kingdom Holding's April 2026 investor deck put the tower at Level 99, about 398 meters, with 274,000+ cubic meters of concrete poured, about 61% of total concrete, façade cladding installed across 36+ floors, MEP first-fix work in progress across office Levels 7-14, and about 6,000 workers operating around the clock (Kingdom Holding 1Q 2026 presentation). Thornton Tomasetti said on April 20, 2026 that the tower had surpassed 100 floors and 400 meters, while a June 22, 2026 Zawya/Refinitiv report said it was near the 104th floor, just over 400 meters, and still on track for August 2028 (Thornton Tomasetti, Apr. 20 2026; Zawya/Refinitiv, Jun. 22 2026).

Evidence

The historical backbone is that very tall towers do finish, but the last phase is slow. In the completed 500-meter-plus reference class, the gap from top-out or exterior structural completion to completion or opening is often about one to two years, and stalled prestige towers can sit for much longer. I used this reference class mainly to size the right tail, not to override the live Jeddah schedule.

ProjectWhat the history saysForecast use
Burj KhalifaTopped out in January 2009 and opened in January 2010 (Burj Khalifa).A clean Gulf megatall can finish about a year after top-out.
Merdeka 118Topped out in 2021 and was completed in 2023 before public inauguration in 2024 (Merdeka 118).Two-year finishing tails happen even without a collapse in work.
Shanghai TowerConstruction started in 2008, topped out in 2013, and completion/opening ran into 2015 (Shanghai Tower).Completion and opening can differ by many months.
Ping An Finance CentreTopped out in 2015 and was completed in 2017 (Ping An Finance Centre).Complex supertall fit-out can take roughly two years after the main structure.
One World Trade CenterThe spire was installed in 2013 and the building opened in 2014 (One World Trade Center).Political and security complexity can still leave an 18-month close-out.
Guangzhou CTF Finance CentreTopped out in 2014 and completed in 2016 (Guangzhou CTF Finance Centre).A 500-meter-plus tower can need more than two years after top-out.
Goldin Finance 117Topped out in 2015 and remained unfinished for years (Goldin Finance 117).A visible megatall structure is not proof of near-term completion.
Dubai Creek TowerFoundation work began, but the original record-tower plan was later halted or redesigned (Dubai Creek Tower).Record-tower projects carry real cancellation or redesign risk.

The Jeddah-specific record is more important than the generic class because the project has both a signed restart contract and a history of missed dates. The full public schedule history I used is below.

Date or source vintageStatus, target, or milestoneHow I used it
2013CTBUH lists Jeddah Tower's construction start in 2013 and current expected completion as 2030 (CTBUH Skyscraper Center).Confirms this is a restarted old project, not a fresh build.
February 2017World Construction Network listed construction as started in 2013 and completion as 2018 (World Construction Network, Feb. 16 2017).The original completion schedule was badly missed.
2017-2018 haltGlobal Construction Review reported that work started in 2013, halted after the 2017 anti-corruption drive, and had 63 of 157 storeys completed when work stopped (Global Construction Review, Oct. 7 2024).The prior multi-year stall is the main reason for a fat right tail.
October 2, 2024Kingdom Holding announced the SAR 7.2 billion completion agreement, 42-month anticipated period, 63 of 157 floors complete, and first-phase infrastructure already executed (Kingdom Holding, Oct. 2 2024).This is the strongest primary-source anchor for a 2028 finish.
December 31, 2025 financial-statement vintageKingdom Holding's 2025 financial statements repeated the 42-month construction expectation and said the company would receive SAR 230 million from SBG on completion of Jeddah Tower in 2028 (KHC 2025 financial statements).A 2028 completion is embedded in audited financial reporting, not just media talk.
January 20, 2025MEED reported that concrete pouring was set to begin on January 20, 2025 and that the superstructure was about one-third complete at 63 of 157 floors (MEED, Jan. 20 2025).Physical work had resumed, but the clock should run from the actual restart as well as the contract date.
March 25, 2026Kingdom Holding said the tower had reached Level 91 at about 370 meters, with façade and MEP work under way, an average five-day floor cycle, about 5,200 workers, and over 8 million work hours without a lost-time incident (KHC 2025 earnings release).Confirms strong mobilization and rapid vertical progress.
April 2026Kingdom Holding reported Level 99, about 398 meters, about 61% of total concrete poured, façade installed on 36+ floors, MEP first-fix on office Levels 7-14, and about 6,000 workers (Kingdom Holding 1Q 2026 presentation).Shows the core is fast, while façade and systems trail the structure.
April 20, 2026Thornton Tomasetti said the tower had surpassed 100 floors and 400 meters (Thornton Tomasetti, Apr. 20 2026).Independent engineering-team confirmation of the 100-floor milestone.
June 22, 2026Zawya/Refinitiv reported project-manager comments that the tower was near the 104th floor, just over 400 meters, rising at about 4 meters per week, and still on track for August 2028 (Zawya/Refinitiv, Jun. 22 2026).The live target still says 2028, but the height and remaining works argue for schedule risk.
Current CTBUH listingCTBUH lists the tower as under construction, 1,000+ meters, 167 floors, and expected completion in 2030 (CTBUH Skyscraper Center).This is the best non-developer counterweight to the 2028 target.

The vendor trail supports real completion intent. KONE announced on October 8, 2025 that it had booked a third-quarter 2025 order for 67 elevators and escalators for Jeddah Tower, including UltraRope systems and two JumpLift construction-time elevators (KONE, Oct. 8 2025). That reduces the probability of abandonment, but it also underlines why the last phase is complex.

I modeled the date as a mixture. I assign 0.3% before 2028, because completion before then would require a very loose interpretation of "complete." For the remaining mass, I used a 35% official-target component centered on September 15, 2028, a 34% normal-slip component centered on June 15, 2029, a 17.5% slow/CTBUH component centered on August 1, 2030, a 9.7% major-interruption tail starting January 1, 2031, and a 3.5% discrete after-2037 or never-completed tail. The resulting year probabilities are 38% in 2028, 29% in 2029, 14% in 2030, 15% in 2031-2037, and 4.2% after 2037.

What's non-obvious

Most coverage treats "100 floors" as if the tower is close to done. Kingdom Holding's own April 2026 data says the opposite: the tower was at Level 99 and 61% of total concrete, but cladding was installed across only 36+ floors and MEP first-fix work was only across office Levels 7-14 (Kingdom Holding 1Q 2026 presentation). The visible core can keep rising while the completion date is still set by façade, vertical transport, MEP, fire/life-safety, spire, and formal close-out.

The other non-obvious point is that the restart is more credible than earlier hope, but not enough to make 2028 the median. The 42-month contract, audited 2028 receivable, KONE order, and 6,000-worker site point to a real push to finish (Kingdom Holding, Oct. 2 2024; KHC 2025 financial statements; KONE, Oct. 8 2025; Kingdom Holding 1Q 2026 presentation). But CTBUH's 2030 entry and the June 2026 report of just-over-400-meter height are strong enough outside-view signals to move the median into 2029 (CTBUH Skyscraper Center; Zawya/Refinitiv, Jun. 22 2026).

Limitations

The largest uncertainty is the resolution definition. This question resolves on the earliest clear statement that tower construction is complete, not on first occupancy or completion of the whole Jeddah Economic City development. If the developer or major media call the tower "construction complete" after exterior close-in while interior fit-out continues, this distribution is too late; if sources wait for a ceremonial opening or CTBUH recognition, it is too early.

The public record is also thin after April 2026. The latest primary progress snapshot I found is Kingdom Holding's April 2026 presentation, and the latest useful public progress report I found before the July 4, 2026 forecast date is the June 22, 2026 Zawya/Refinitiv summary of project-manager comments (Kingdom Holding 1Q 2026 presentation; Zawya/Refinitiv, Jun. 22 2026). Private data on façade fabrication, elevator installation, concrete pumping above current height, Saudi Binladin cash flow, inspections, and commissioning would move the forecast most.

Sources

  1. Domain Expert Search · mcp

    Found 14 subagent groups for 'Jeddah Tower Saudi megaproject construction status schedule contractor completion risks developer incentives':

  2. News · mcp

    Tool news_search on news returned an error:

  3. errors.pydantic.dev · tool
  4. AskNews · mcp

    [Date range of 549 days split into 4 chunks (160-day API limit)]

  5. tuniscope.com · tool
  6. Rega Saudi · mcp

    Tool rega_saudi_get_price_trends on rega-saudi returned an error:

  7. errors.pydantic.dev · tool
  8. Saudi mof · mcp

    Tool saudi_mof_get_macroeconomic_data on saudi-mof returned an error:

  9. siasat.com · tool
  10. gulfnews.com · tool
  11. dezeen.com · tool
  12. bizjournals.com · tool
  13. tradearabia.com · tool
  14. bizjournals.com · tool
  15. constructionreviewonline.com · tool
  16. bizjournals.com · tool
  17. zawya.com · tool
  18. newsweek.com · tool
  19. Wathq · mcp

    Tool wathq_lookup_cr_national_number on wathq returned an error:

  20. Claude Code · e2b

    Job coding_whiz_job_11d0e28114 done after 565912ms.

  21. Domain Expert Research Task · mcp

    Job domain_expert_research_task_bb38054bd4 done after 209742ms.

  22. chartstorm.info · tool
  23. foreignexchanges.news · tool
  24. mekongmemo.com · tool
  25. asiasentinel.com · tool
  26. construction-physics.com · tool
  27. asiasentinel.com · tool
  28. asiasentinel.com · tool
  29. theovershoot.co · tool
  30. worksinprogress.news · tool
  31. jessemarks.substack.com · tool
  32. chinamenanewsletter.substack.com · tool
  33. architecturaldigest.com · tool
  34. kingdom.com.sa · tool
  35. ctbuh.org · tool
  36. concreteconnect.co.uk · tool
  37. science.howstuffworks.com · tool
  38. chicagobusiness.com · tool
  39. spa.gov.sa · tool
  40. archup.net · tool
  41. gulfconstructiononline.com · tool
  42. newsweek.com · tool
  43. thorntontomasetti.com · tool
  44. constructionbriefing.com · tool
  45. constructionweekonline.com · tool
  46. newsweek.com · tool
  47. burjdubai.com · tool
  48. news.bbc.co.uk · tool
  49. business24-7.ae · tool
  50. gulfnews.com · tool

Question Details

Description

This question asks for the calendar date on which construction of the Jeddah Tower (also known as Kingdom Tower) in Jeddah, Saudi Arabia is completed. Jeddah Tower is planned to exceed 1,000 meters in height and become the tallest building in the world. Construction began in 2013 but experienced long delays and a multi-year pause before resuming around 2024–2025. As of early 2026, construction has progressed past roughly 80–100 floors, with work advancing steadily again. ([jeddahconstruct.com](https://www.jeddahconstruct.com/)) Current public estimates from developers and reporting suggest a target completion around 2028, though timelines have historically shifted. ([agbi.com](https://www.agbi.com/real-estate/2025/11/jeddah-tower-world-tallest-building-homes-to-go-on-sale-in-2026/)) The question resolves to the date when the tower is officially considered complete (see criteria below).

Resolution Criteria

The question resolves to the first calendar date on which Jeddah Tower is officially declared complete by its developer (Jeddah Economic Company), the Saudi government, or widely accepted international business or construction media (e.g., Reuters, Bloomberg, Financial Times), indicating that construction has been finished. "Complete" is defined as structural and architectural construction being finished to the point that the building is no longer under construction, even if interior fit-out, tenant occupancy, or surrounding infrastructure continues afterward. If multiple dates are reported, the earliest date of a clear and widely reported declaration of completion will be used.

Fine Print

- “Completion” refers to completion of construction of the tower itself, not the broader Jeddah Economic City development. - Temporary pauses or resumptions do not affect resolution unless they change the final completion date. - Minor discrepancies between sources (e.g., ceremonial opening vs. construction completion) will be resolved in favor of the earliest clear statement that construction is finished. - If the tower is cancelled or never completed this question will resolve above the upper bound date.